Road closures round here in numbers

Every road closure booked on the councils' and utilities' records round Saffron Walden, Thaxted, Great Dunmow and Haverhill since July 2020, when the Department for Transport's Street Manager started. Worked out Tue 24 Nov 23:24.

Over the years

Year by year

YearRoad closuresCancelledTypical length (days)A week or moreEmergenciesSets of traffic lights
2026 (so far)3,86530%3.019%3933,211
20253,30431%3.018%2183,195
20242,72834%3.017%1952,956
20232,67635%3.019%1144,137
20222,35733%4.025%764,003
20212,45535%3.021%1104,242
2020 (from July)85723%4.028%431,745

Road closures that went ahead (or are still booked) by the year they start; cancelled is the share of those booked that never happened; a typical closure is the median booked length. 2020 counts from July, when Street Manager started, and its first months are low: works booked under the old system before then aren't in Street Manager's records.

In detail: in 2023

2,676road closures went aheadof 4,090 booked
35%of booked closures were cancelled1,414 never happened
1,049different roads closedat least once
3.0 daysa typical closure19% booked for a week or more

Closures a month

Jan: 275 closuresJan275Feb: 205 closuresFebMar: 242 closuresMarApr: 249 closuresAprMay: 263 closuresMayJun: 189 closuresJunJul: 245 closuresJulAug: 215 closuresAugSep: 223 closuresSepOct: 244 closuresOctNov: 208 closuresNovDec: 118 closuresDec118

Closures that went ahead (or are still booked), by the month they start. Temporary traffic lights are counted apart: 4,137 sets in 2023.

The numbers as a table
MonthClosures
Jan 2023275
Feb 2023205
Mar 2023242
Apr 2023249
May 2023263
Jun 2023189
Jul 2023245
Aug 2023215
Sep 2023223
Oct 2023244
Nov 2023208
Dec 2023118

Booked, and what happened

  • 35% were cancelled. 1,414 of 4,090 booked closures never happened, so a closure on the records isn't certain until it starts. We say when a closure is marked as started.
  • 13% were extended after they were booked (361 closures), usually by about 4 days.
  • 28% finished more than a day early (458 of the 1,653 marked as finished).
  • 114 were emergencies: burst pipes, gas leaks and the like, closed with no notice.

How long they last

  1. Under a day639
  2. 1 to 3 days753
  3. 3 days to a week767
  4. 1 to 4 weeks410
  5. Over 4 weeks107

Who closes the roads

  1. Essex County Council350
  2. Anglian Water317
  3. Cambridgeshire County Council310
  4. BT300
  5. Affinity Water293
  6. Hertfordshire County Council213
  7. Cambridge Water Company191
  8. UK Power Networks Eastern & London185
  9. Suffolk County Council132
  10. Gigaclear108

By the organisation doing the work. The councils' own count includes road repairs, resurfacing and improvements.

Why

  1. Water815
  2. Road repairs and resurfacing567
  3. Phone and broadband477
  4. Road improvements392
  5. Electricity209
  6. Railway102
  7. Gas65
  8. An event45

The roads closed most often

  1. Station Road, Dullingham14
  2. Church Lane, Braintree14
  3. High Street (C233), Cambridge14
  4. Hadham Road, Bishop's Stortford13
  5. Brookhampton Street, Ickleton12
  6. East End, Furneux Pelham10
  7. North Street, Great Dunmow10
  8. Bardfield Road, Thaxted10
  9. Great Hadham Road, Much Hadham10
  10. London Road, Little Wilbraham10
  11. Station Road, Fulbourn10
  12. Ongar Road, Great Dunmow9

Each closure booked on the road counts once, however long it lasted.

By council

  1. Essex County Council1,232
  2. Cambridgeshire County Council819
  3. Suffolk County Council328
  4. Hertfordshire County Council291
  5. National Highways6

How we count

A closure is any works or activity whose traffic management is a road closure, counted by its booked start. Street Manager replaced the old system (EToN) in July 2020; its monthly archive has every record since, and we've read it live since 17 November 2026. Cancelled means Street Manager says so. Extended means its booked end moved later after it was first booked. Finished early compares when it was marked as stopped with its booked end. We don't count overruns: works are often marked as stopped days after they really end, so the records can't tell an overrun from late paperwork. Type of works is worked out from who's doing them (a water company, a broadband firm…) and what Street Manager calls them. Essex County Council records nearly all its own works as improvements, where the other councils call theirs repairs, so road repairs and road improvements are best read together. National Highways' own closures feed (motorways and trunk roads) isn't in these numbers yet: the National Highways works counted here are the ones they record in Street Manager. Contains public sector information licensed under the Open Government Licence v3.0.